Clear Creek Trail - Phases 6 & 7

Clear Creek Trail to Extend to Tiffin


The Clear Creek Trail runs south of Highway 6 along Clear Creek for 4.3 miles. The trail has been extended from east of Deer Creek Road to Creekside Ballpark; this extension opened in 2019.

Trail work north of I-80 involves crossing under multiple I-80 and I-380 bridges. Once those trail connections are complete, the Clear Creek Trail will
 connect with Tiffin's Clear Creek Trail west of I-380.

The trail segments that go under the I-80 and I-380 bridges are not expected to open until 2024 and there are no temporary connections. These segments will be constructed as part of the I-80/380 Systems Interchange project, and will be constructed after the new I-80 and I-380 bridges over Clear Creek are complete.

Highlights


After all work is complete, the 1.9 mile section of trail will feature:
  • 10' wide paved trail
  • Two bridge crossings over Clear Creek
  • Multiple crossings under interstate bridges
  • Connection to Tiffin's Clear Creek Trail

Cost


  • Received $1,112,600 in federal funds
  • Bid in January 2018
  • Low bid: $1,758,552.84 (Iowa Bridge and Culvert of Washington, Iowa)

Timeline


  • Start: March 2018
  • Estimated trail opening: The timeline for this project has been impacted by changes to the I-80/I-380 interchange bridge construction schedule. Connections under I-80 and I-380 will not be made until 2024.
Clear Creek Trail sign

Contact Us

  1. Dan Holderness


    City Engineer
    Email

    Scott Larson


    Assistant City Engineer
    Email

    1512 7th St.
    P.O. Box 5127
    Coralville, IA  52241

    Ph: 319.248.1720
    Fx: 319.248.1894

    Staff Directory
*Updated August 27, 2020